DA to insist Eskom invoke penalty clauses over Hitachi’s Medupi, Kusile delays

Business Day Live 24 August 2012.

THE Democratic Alliance (DA) says it will write to Eskom CEO Brian Dames to insist that the appropriate penalty clauses be invoked in the contract with Hitachi Power Africa, which is building and installing the boilers at the Medupi and Kusile coal power stations.

Earlier this week Eskom chief financial officer Paul O’Flaherty told Parliament’s portfolio committee on energy that the challenges Eskom was experiencing in its power station programme were in part because of delays by Hitachi in meeting boiler delivery deadlines…

http://www.bdlive.co.za/business/energy/2012/08/24/da-to-insist-eskom-invoke-penalty-clauses-over-hitachis-medupi-kusile-delays